I have a server that has become unstable.
My tasks in the next 2 days:
Complete a full system backup of the source server
complete a full system restore to the destination server
unplug the old system
plug in the new system
Backup / Restore software: Veritas Backup Exec
Because of the nature of the production box, we have a No down time policy.
My concern is will replication be broken.
What might you suggest I prepare for?
Typically, you'll need to script out replication and reinitialize when you're
up and going on the new server. You can do a nosync initialization provided
all data has been synchronizes and then you have prevented access to the
system while this project is being done.